Budimex S.A. wins tenders for key sections of the S10 Szczecin – Piła road

Budimex's bids for 5 key sections of the S10 Szczecin – Piła expressway were considered the most advantageous by the contracting authority: the General Directorate for National Roads and Motorways, Szczecin Branch. The total length of these sections will be 74 kilometres, which is more than 70% of the length of the new expressway from Stargard Szczeciński to Piła. The investment will be implemented in the Design and Build formula.

Over 100 km of new expressway

The S10 will be a dual carriageway expressway with two lanes in each direction. The decision on environmental conditions issued in July last year is final and has determined the route of the route. The new S10 expressway will bypass the towns through which the current DK10 runs, including Suchań, Recz, Kalisz Pomorski and Mirosławiec. The new route will connect with the already existing Wałcz bypass, and further on, the S10 will run south of the existing DK10. At the Piła Północ junction - the future connection of the S10 and S11 - the Stargard - Piła section will end. Eleven road junctions are planned for the route. There will also be five pairs of Motorway Service Areas and two Road Maintenance Circuits.

From Szczecin to Toruń in 2023

The S10 road, with a length of approx. 410 km, will connect Szczecin via Piła, Bydgoszcz and Toruń with the Warsaw agglomeration. The completion of all missing sections is included in the Government Programme for the Construction of National Roads until 2030. It will be a direct connection between the regions of Western Pomerania, the north of Wielkopolska, Kuyavian-Pomeranian Voivodeship and Mazovia. Thanks to this road, an alternative transport route will be created to the north of the A2 motorway.

Budimex submitted the most advantageous offers for the following sections:

 

Section 8: Witankowo Interchange – Piła North Interchange – 13 km

Offer value: PLN 586,422,080.00 net

Date of commencement of works: from the date of conclusion of the contract by both parties

Completion date: 39 months from the date of conclusion of the contract (winter periods are not included in the duration of the works)

Warranty period for major works: up to 15 years

Warranty period: 60 months from the date indicated in the Takeover Certificate

 

Section 7: Piecnik – Wałcz West – 16 km

Information date: 19.02.2024

Offer value: PLN 448,960,288.00 net

Completion date: 39 months from the date of conclusion of the contract, excluding winter periods

Warranty period: up to 15 years, warranty period: 60 months

 

Section 6: Łowicz Wałecki Interchange – Piecnik Interchange – 15 km

Offer value: PLN 437,439,230.00 net

Completion date: 39 months from the date of conclusion of the contract, excluding winter periods

Warranty period: up to 15 years, warranty period: 60 months

 

Section 5: Cybowo Interchange – Łowicz Wałecki Interchange – 16 km

Offer value: PLN 492,089,901.00 net

Completion date: 39 months from the date of conclusion of the contract, excluding winter periods

Warranty period: up to 15 years, warranty period: 60 months

 

Section 2: Stargard East Junction – Suchań Junction – 14 km

Offer value: PLN 366,166,760.93 net

Date of commencement of works: from the date of conclusion of the contract by both parties

Completion date: 39 months from the date of conclusion of the contract (winter periods are not included in the duration of the works)

Warranty period for major works: up to 15 years

Warranty period: 60 months from the date indicated in the Takeover Certificate

Budimex S.A.'s bids were rated the highest in tender procedures, which proves trust and appreciation for the company's experience and competence in the implementation of large infrastructure projects. It should be noted that despite the high evaluation of the bids, the tender procedures for the evaluation of the bids have not yet been finalised.

–––––––

BUDIMEX SA is a company with over fifty years of tradition, which has a significant contribution to the economic development of Poland. With our work, we improve the quality of life of millions of Poles. During the 50 years of our existence, we have completed thousands of modern infrastructure, construction and industrial investments. The culture of innovation, improvement and following the principles of sustainable development allowed us to gain the position of a leader in the Polish construction market. Not only are we present on the Polish market, but also abroad. We gradually increase our involvement in the facility management (operation of real estate and infrastructure facilities) and waste management sectors. Since 1995, our company has been listed on the Warsaw Stock Exchange, and since 2011 it has been included in the ESG index – gathering the most responsible companies on the stock exchange. Its strategic investor is a Spanish company with global reach – Ferrovial. The group includes: Mostostal Kraków and FBSerwis.

We are one of the signatories of the Agreement for Safety in Construction – an initiative established in 2010, bringing together the largest general contractors in Poland in order to improve occupational safety in the construction industry.

More information is available at www.budimex.pl/en

ATTACHMENTS

s6 zrealizowane przez budimex na pomorzu 1

s6 zrealizowane przez budimex na pomorzu 1

s6 zrealizowane przez budimex na pomorzu 2

s6 zrealizowane przez budimex na pomorzu 2

s6 zrealizowane przez budimex na pomorzu 3

s6 zrealizowane przez budimex na pomorzu 3